Success story behind 500kV Circuit-3 transmission line project
Unity in action
The 500kV Circuit-3 Quang Trach - Pho Noi transmission line spans nearly 520km, consisting of two double-circuit lines connected by 1,177 tower foundation points. It passes through 211 communes/wards in 43 districts/towns across nine provinces from North Central Vietnam to the northern region. On August 28, 2024, over seven months after the groundbreaking on January 18, the project was completed within a record-short time frame despite massive and challenging workload, and complicated terrain and weather conditions.
2,500 engineers and workers from EVN have participated in the construction of the 500kV Circuit 3 transmission line |
Within four months, from June to October 2023, Vietnam Electricity (EVN), the National Power Transmission Corporation (EVNNPT), along with the Ministry of Industry and Trade, the Ministry of Agriculture and Rural Development, the Ministry of Natural Resources and Environment, and nine provinces through which the transmission line passes, have completed investment procedures for all the four component projects.
At the end of October 2023, a groundbreaking ceremony was held for the 500kV Nam Dinh 1 - Pho Noi transmission line project. This was the first component project of the transmission line, successfully energized on June 30, 2024.
The remaining component projects, along with the newly invested 500kV Thanh Hoa substation and the expansion of the bays at two existing substations (500kV Pho Noi substation and 500kV Quang Trach substation), were simultaneously started on January 18, 2024.
Under the guidance of the Prime Minister, and with the participation of the entire political system, the 500kV Circuit-3 Quang Trach - Pho Noi transmission line project has become a notable highlight.
Identified as a key and urgent project of particular importance to national energy security, especially for the northern region, this project significantly enhances the power transmission capacity of the North-Central region from approximately 2,200 MW to about 5,000 MW, contributing significantly to ensuring electricity supply for the North. Therefore, within just seven months from the groundbreaking to the project’s completion, Prime Minister Pham Minh Chinh presided over 10 meetings, visited the construction site to inspect, encourage workers, and extended his gratitude to local residents who gave up their land for the project.
Meanwhile, Deputy Prime Ministers conducted direct inspections to monitor the project’s construction progress and the supply of materials and equipment. From March to June 2024, the State Steering Committee for Key National Energy Projects held biweekly online meetings with leaders from relevant ministries, agencies, and nine provinces through which the transmission line passes. These meetings focused on updating progress, addressing obstacles, and resolving challenges.
As a result, the land clearance process was completed in just over three months, making it the fastest for any 220-500kV power transmission project ever implemented, enabling construction units to accelerate the project.
The 500kV Circuit-3 Quang Trach - Pho Noi transmission line project involves a significant construction workload |
Mobilizing maximum resources
The 500kV Circuit-3 Quang Trach - Pho Noi transmission line project involves a significant construction workload and applies numerous new technologies.
Although the total length of the entire line is about 519km, it is designed to consist of two double-circuit lines, making the total length 1,038km. The project requires a large volume of equipment, including nearly 139,000 tonnes of steel towers with approximately 83 percent domestically produced and 17 percent imported.
Throughout the construction process, the project faced unfavorable and unpredictable weather conditions. To achieve the set goals, the electricity sector mobilized a large workforce to support contractors on the construction site.
At the peak of construction, up to 15,000 workers from contractors and various units of the EVN Group, Viettel Military Industry and Telecoms Group, Vietnam Oil and Gas Group (PVN), and Vietnam Posts and Telecommunications Group (VNPT), participated in tower construction and line stringing.
The “on-site” approach has proven highly effective (on-site construction equipment, on-site labor, on-site building materials, and on-site compensation).
Thanks to this approach, over 2,000 pieces of construction machinery, approximately 95 percent of the building materials and around 90 percent of the general labor force, including over 7,000 workers from hundreds of businesses and organizations, have been mobilized for foundation excavation and transportation of materials and equipment.
Approximately 83 percent of the steel poles were domestically manufactured, requiring contractors to enhance production capacity and foster mutual support among contractor units.
The Quang Trach - Pho Noi 500kV Cuircui-3 transmission line project has been completed on schedule. Energy experts believe “splitting” the bidding packages has helped maximize the mobilization of social resources to ensure the project’s progress./.
See more news
Ministry proposes incentives for renewable energy projects
16:17 | 20/12/2024 Energy
Small nuclear reactors could power Vietnam’s net-zero future: experts
09:16 | 17/12/2024 Energy
Việt Nam needs a competitive energy market: experts
16:59 | 08/12/2024 Energy
Việt Nam resumes nuclear power project amid rising energy demands
17:07 | 07/12/2024 Energy
Reviving nuclear power programme believed a correct policy
09:09 | 02/12/2024 Energy
Viet Nam to restart Ninh Thuan nuclear power project
20:27 | 01/12/2024 Energy
Chinese corporation interested in waste-to-energy plant in Can Tho
15:57 | 29/11/2024 Energy
Vietnam seeks Danish assistance in green energy development
11:21 | 26/11/2024 Energy
Huge potential for VN, UK to boost cooperation in clean energy
15:29 | 25/11/2024 Energy
Solutions discussed to ensure coal supply for electricity generation in 2025
16:24 | 19/11/2024 Energy
HGS affirms ground service quality in aviation sector
17:19 | 23/12/2024 Companies
Banking sector: Capital flows with no congestion
17:13 | 23/12/2024 Finance-Banking
VAECO contributes to elevating Vietnamese aviation brand
17:11 | 23/12/2024 Vietnamese Brands
Amended Electricity Law proves MoIT’s institutional improvement success
17:06 | 23/12/2024 Policy
FTAs enhance Vietnam-China trade growth
17:02 | 23/12/2024 Cooperation
Multimedia
Glorious tradition of the Vietnam People's Army
08:30 | 22/12/2024 Infographic
Total FDI registered in Vietnam hits 31.4 billion USD in January-November
09:02 | 17/12/2024 Infographic
First 11 months of 2024: Import-export turnover increases 15.4%
10:55 | 16/12/2024 Infographic
11-month agro-forestry-fishery exports exceed yearly target
19:55 | 15/12/2024 Infographic
Hanoi achieves or exceeds 23/24 socio-economic targets for 2024
08:57 | 13/12/2024 Infographic
Amended Electricity Law proves MoIT’s institutional improvement success
17:06 | 23/12/2024 Policy
Ministry proposes extending agricultural land tax exemption through 2030
15:06 | 23/12/2024 Policy
Gov't targets to gradually make English second language at schools by 2030
15:45 | 21/12/2024 Policy
Nine newly-adopted laws made public
16:42 | 20/12/2024 Policy
Success story behind 500kV Circuit-3 transmission line project
16:43 | 23/12/2024 Energy
Ministry proposes incentives for renewable energy projects
16:17 | 20/12/2024 Energy
The Era of Advancement for Vietnam Industrial Park
17:15 | 19/12/2024 Industry
Vietnamese coffee sector working to meet EU Deforestation Regulation
16:38 | 18/12/2024 Industry
Nghe An Southeast Economic Zone aims to attract 1 billion USD in FDI in 2025
12:33 | 21/12/2024 Investment
Boeing aims to expand investment and cooperation in Vietnam’s defense sector
17:00 | 19/12/2024 Investment
Can Tho attracts non-state investment
10:21 | 17/12/2024 Investment
FDI remains vital contributor to boost economic growth
09:06 | 13/12/2024 Investment
Banking sector: Capital flows with no congestion
17:13 | 23/12/2024 Finance-Banking
Year-end surge in property bond issuance amid financial challenges
09:39 | 20/12/2024 Finance-Banking
Vietcombank named most valuable brand in Vietnam
16:43 | 18/12/2024 Finance-Banking
Many banks increase deposit interest rates in year-end period
16:56 | 16/12/2024 Finance-Banking
Vietnam likely to face continued turbulent weather systems in 2025
14:26 | 19/12/2024 Environment
Nature-based projects help Mekong Delta fight climate change
16:31 | 18/12/2024 Environment
11 rare monkeys released back into wild in Nghe An
09:27 | 18/12/2024 Environment
Master Plan on Sustainable Exploitation and Use of Coastal Resources announced
11:26 | 16/12/2024 Environment
Contracts worth 286.3 million USD inked at Vietnam Int’l Defence Expo 2024
17:02 | 22/12/2024 Science - Technology
Vietnam can partner with UK in developing nuclear power: Expert
12:43 | 21/12/2024 Science - Technology
Vinaphone launches fastest 5G service in Vietnam
12:38 | 21/12/2024 Science - Technology
Vietnam cooperates with Google to launch “Official Government Apps" feature
17:13 | 20/12/2024 Science - Technology
30-day free rides on 17 bus routes connected to Metro Line 1
16:14 | 23/12/2024 Society
Bac Ninh: 28 additional 4-star-rated OCOP products
23:24 | 22/12/2024 Society
HCM City’s first metro line launched after years of delay
16:47 | 22/12/2024 Society
Aviation sector strengthens smuggling, commercial fraud and counterfeit goods control
09:49 | 22/12/2024 Society
VAECO contributes to elevating Vietnamese aviation brand
17:11 | 23/12/2024 Vietnamese Brands
Petrovietnam keeping national “energy flame” ever burning
16:17 | 23/12/2024 Vietnamese Brands
Vietnamese products crave out a niche in UK market: Official
15:26 | 23/12/2024 Vietnamese Brands
Viettel's hi-tech products meets standards for supply to Malaysia
13:19 | 21/12/2024 Vietnamese Brands
Fireworks to light up sky over Hanoi on New Year celebration
15:13 | 23/12/2024 Culture
Vietnam’s high-end fashion targets Chinese market
10:04 | 22/12/2024 Culture
Enduring tradition of Ha Nhi ethnic minority group's costumes
13:14 | 21/12/2024 Culture
Legendary band Boney M to thrill Vietnamese audiences this Christmas
14:49 | 17/12/2024 Culture
Vietnam a green, attractive destination
16:30 | 23/12/2024 Tourism
Mekong Delta tourism continues to surge
15:21 | 23/12/2024 Tourism
Ben Thanh-Suoi Tien metro line - catalyst for HCM City's tourism development
15:17 | 23/12/2024 Tourism
Overseas tourism promotion: Breakthrough in market connectivity
14:46 | 23/12/2024 Tourism