Construction of 500kV circuit 3 transmission line accelerated
According to the Southern Power Corporation (EVNSPC), 779 people from the corporation are currently present on the construction site of the project. They include engineers, workers, safety officers, and a skilled and highly qualified command staff.
![]() |
Workers from the Southern Power Corporation assemble crossbeam structures - photo: EVNSPC |
EVNSPC has informed that in the near future, the corporation will mobilize an additional 188 people, bringing the total number of people present on the construction site of the project to 967.
These people are working together with the highest determination to ensure the project is completed on schedule before June 30, 2024, in accordance with the directive of the Prime Minister.
For example, the Soc Trang Power Company has been tasked to build and install steel tower 171 in Dong Hoang Commune, Dong Son District, Thanh Hoa Province. The company has completed some relevant items and is now striving to carry out the next tasks.
According to the Soc Trang Power Company, it has sent a total of 32 people to the construction site of the project, including workers and technical staff. The entire team has gotten up to speed on the work, grasped the construction plan, and has already begun implementing the site clearance and leveling work. They have received about 40 percent of the materials and transported them to the tower foundation.
The team from the Soc Trang Power Company will continue to receive and sort materials and equipment for related accessories. They will also start the assembly and erection of the tower segments and arms when they have enough materials for the base section and arm segments.
![]() |
Workers from the Soc Trang Power Company at the construction site of the Quang Trach - Pho Noi 500kV - circuit 3 transmission line project - photo: EVNSPC |
According to the Soc Trang Power Company, the current difficulty is that the contractor has yet to provide enough materials and accessories for the base sections. The team has urged the contractor to urgently provide the materials to be transported to the construction site, prioritizing the materials for the tower base sections, in order to better implement the work.
Previously, in response to the call from the leadership of EVNSPC to provide additional human resources for the 500kV transmission line - circuit 3 project, 12 staff members and workers of the Soc Trang Power Company have voluntarily requested to be sent to the construction site of the project.
“As a worker of the power industry, I wish to participate in the 500kV transmission line - circuit 3 project with strong determination to complete it on schedule,” Nguyen Ngoc Duy, born in 1988, a worker from the Tran De power transmission line and transformer station management team, wrote in his letter.Nguyen Anh Khoa, a worker at the Soc Trang City Power Company, also expressed his determination, “I am ready to voluntarily accept the assigned mission, and together with my comrades within and outside the power industry, I will strive my utmost to complete the task seriously, safely and on schedule.”
All members of Vietnam Electricity (EVN) are eager to join the 1,500 representatives from the group who are already at the project construction site to complete it as expected by the Government.
See also

Vietnam sets ambitious targets in revised national power development plan
18:56 | 17/04/2025 Industry

Vietnam developing wind turbine blades that align with weather conditions
16:39 | 13/04/2025 Industry

Ensuring stable power supply during peak summer demand
16:32 | 11/04/2025 Industry

Vietnam, Japan forge 25-year oil and gas partnership
16:58 | 01/04/2025 Industry

Tra Vinh approves investment policy for five more wind power projects
16:09 | 29/03/2025 Industry

Nuclear power plant development in Vietnam: Many key steps taken
17:37 | 22/03/2025 Industry
See more news

PM sets higher requirements for 500 kV Lao Cai – Vinh Yen transmission line project
22:25 | 16/03/2025 Industry

Vietnam's oil venture in Algeria advances to second phase with promising results
18:49 | 15/03/2025 Industry

Vietnam, US look to strengthen comprehensive energy cooperation
18:07 | 15/03/2025 Industry

Call for increased use of hydrogen energy in Vietnam
17:36 | 10/03/2025 Industry

Resolution on special mechanisms for Ninh Thuan nuclear power project investment
14:44 | 27/02/2025 Industry

Breaking barriers to lure private investment for energy growth: insiders
11:52 | 27/02/2025 Industry

Vietnam, RoK strengthen energy cooperation
15:59 | 26/02/2025 Energy

Building a foundation for Vietnam to develop nuclear power
16:21 | 24/02/2025 Energy

Reasonable electricity prices to attract investment in Vietnam’s energy sector
15:59 | 21/02/2025 Energy

PM approves plan to shift from coal to clean energy
16:39 | 18/02/2025 Energy

Historical significance of International Workers’ Day
09:22 | 28/04/2025 Society

Imexpharm sets breakthrough growth goals at 2025 shareholders meeting
10:00 | 27/04/2025 Vietnamese Brands

Streamlining State apparatus to expand development space
13:31 | 26/04/2025 Society

Vietnam-Laos relations vital to revolutionary cause in each country: State leader
10:05 | 26/04/2025 Cooperation

US calls tariff talks with Vietnam productive
09:02 | 26/04/2025 News and Events
Multimedia

Proposed names for 34 provincial-level administrative units after mergers
16:42 | 16/04/2025 Infographic

Vietnam-China Comprehensive Strategic Cooperative Partnership
15:55 | 14/04/2025 Infographic

Vietnam's economy thrives in Q1 2025
16:45 | 12/04/2025 Infographic

Infographic: Gold prices fluctuate following US retaliatory tariff announcement
21:45 | 04/04/2025 Infographic

Seven key missions of the National Data Association
20:07 | 30/03/2025 Infographic

14th National Party Congress’s draft documents more revolutionary, action-oriented, highly feasible: PM
16:31 | 16/04/2025 Policy

Party chief requires no disruptions to operations throughout restructuring process
16:12 | 14/04/2025 Policy

District-level local governments to cease operations from July 1: draft law
16:53 | 13/04/2025 Policy

Australian scholar praises Vietnam’s remarkable 50-year transformation
16:28 | 12/04/2025 Policy

Hanoi to develop 254-million-USD industrial cluster
21:13 | 19/04/2025 Industry

Vietnam sets ambitious targets in revised national power development plan
18:56 | 17/04/2025 Industry

Prime Minister urges COMAC to support Vietnam in developing aviation industry
17:12 | 14/04/2025 Industry

Steel industry seeks solutions amid tariff "shock"
17:12 | 13/04/2025 Industry

Ho Chi Minh City’s FDI rebound attracts high-tech giants
21:23 | 19/04/2025 Investment

Korean firms encouraged to invest more in Vietnam’s energy sector
16:31 | 15/04/2025 Investment

Public investment aimed to drive Vietnam’s economic growth
10:48 | 15/04/2025 Investment

Hue calls for investment in the Chan May – Lang Co Economic Zone
23:36 | 11/04/2025 Investment

Remittances to HCM City reach over 2.41 billion USD in first quarter
08:21 | 20/04/2025 Finance-Banking

National committee meets to accelerate ODA, concessional loan disbursement
14:43 | 15/04/2025 Finance-Banking

Vietnam accelerates rollout of 500 trillion VND credit package for infrastructure and technology firms
15:36 | 12/04/2025 Finance-Banking

Hong Kong paves way for Vietnam–China finance link
19:25 | 10/04/2025 Finance-Banking

Vietnam's carbon market: Prudent approach to avoid costly outcomes
08:53 | 18/04/2025 Environment

Moc Chau Milk centers on green development and growth
16:06 | 17/04/2025 Environment

Extra efforts requested to address forest fire consequences in Quang Ninh
16:56 | 16/04/2025 Environment

Hanoi to host major green growth summit this month
16:44 | 11/04/2025 Environment

PM applauds youth entrepreneurship at National Startup Day for Students
21:40 | 20/04/2025 Science - Technology

Nuclear energy development to facilitate green transition: Conference
22:10 | 18/04/2025 Science - Technology

HCM City seeks stronger hi-tech cooperation with US, Japan, RoK
16:47 | 15/04/2025 Science - Technology

Da Nang, RoK to train next generation of Vietnamese software experts
13:24 | 11/04/2025 Science - Technology

Historical significance of International Workers’ Day
09:22 | 28/04/2025 Society

Streamlining State apparatus to expand development space
13:31 | 26/04/2025 Society

Vietnam steadily marches into new era of growth
16:35 | 21/04/2025 Society

Workers proactively enhance productivity in new era
15:32 | 21/04/2025 Society

Imexpharm sets breakthrough growth goals at 2025 shareholders meeting
10:00 | 27/04/2025 Vietnamese Brands

Petrovietnam: New milestone - New vision for sustainable development
16:21 | 21/04/2025 Vietnamese Brands

Vietnam Oil and Gas Group renamed Vietnam National Industry - Energy Group
22:18 | 10/04/2025 Vietnamese Brands

Vietnamese enterprises float products at world's largest startup fair in India
21:59 | 05/04/2025 Vietnamese Brands

Vietnamese cultural values introduced to international friends in Mexico
20:55 | 30/03/2025 Culture

Hung Kings’ Festival 2025: a grand celebration of culture and heritage
15:21 | 30/03/2025 Culture

Vietnam works to seek UNESCO status for Binh Dinh martial arts
18:00 | 29/03/2025 Culture

Nghe An to host ASEAN exhibition this May
16:47 | 24/03/2025 Culture

Digitization key to tourism breakthroughs
09:15 | 24/04/2025 Tourism

Highland products, soul of Son La’s community-based tourism
09:34 | 17/04/2025 Tourism

Vietnam’s scenic landscapes attract Hollywood filmmakers
15:15 | 30/03/2025 Tourism

Positioning unique tourism products to enhance attractiveness of Vietnamese cities
17:56 | 29/03/2025 Tourism